Procedure: (concrete-mount version) Illustration 2.4; Photos 2.4.c, .d
The PED enclosure can be mounted to a concrete pad using the optional mounting
bracket. The bracket is mounted inside the rear of the enclosure using two (2) hex
bolts and washers. Two (2) 0.5” oblong mounting holes are provided in the bracket
to mount the enclosure to the concrete pad. Two (2) 3/8” J-bolts must be placed in
the pad as specified and two conduits (utility and cable output) should be placed
centered in front of these bolts. If required, an 8’ dedicated ground rod should be
placed near the utility conduit. To mount the enclosure to the pad, use a 3/8” lock
washer and nut on each mounting bolt.
NOTE: The enclosure must be mounted on a flush smooth surface and not over-
torqued to prevent damage. Alpha Technologies is not responsible for damages
incurred to the enclosure by improper mounting on uneven surfaces.
Before proceeding, remove the MTA (if installed) and universal bracket (UB1) from
the PED.
1. Install the concrete mounting bracket on the enclosure using the included
bolts, washers and nuts. Insert the bolts from the outside of the enclosure.
2. Center the enclosure over the utility and cable conduits. Align the oblong
holes in the mounting bracket with the 3/8” J-bolts. Secure the enclosure
with a lock washer and nut.
3. Reinstall the UB1 Bracket and place the MTA onto this bracket. Tighten the
captive on the bottom of the UB1 to secure the MTA, (see section 2.9
MODULAR TRANSFORMER ASSEMBLY and 2.7 CONNECTING UTILITY
POWER).
2.4 Pedestal-mount Installations,
continued
PED Mounting
Holes
Pad Mounting Slots
2. INSTALLATION
14
Photo 2.4.c
Concrete Mount and Hard-
ware
Photo 2.4.d
Concrete Mounting Bracket Detail